Original Cost
₹1474 Cr
Baseline estimate
Revised Cost
₹1474 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1474 Cr
Budget left
Spent
₹0 Cr
Remaining
₹1474 Cr
Total
₹1474 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2029
Revised Completion
Completed
Project is within original budget of ₹1474 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹1474 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.