Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

One Time Improvement of Left Out Portion of NH-80 from km. 119.885 (Dogachhi) to km. 132.895 (Zero Mile, Bhagalpur) on EPC mode in the state of Bihar

#562
Road Division Bhagalpur.
East Bihar Road Circle Bhagalpur
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹9.83 Cr
Length13.01 km
Start07-01-2023
Completion06-10-2023
MDR · Simanchal Wing
Road Division Bhagalpur.
Ms. Niranjan Sharma

Project Details

Project No.562
WingSimanchal Wing
DivisionRoad Division Bhagalpur.
CircleEast Bihar Road Circle Bhagalpur
Road TypeMDR
HeadPLAN

Cost & Timeline

Agreement Value₹9.83 Cr
Sanctioned Length13.01 km
ContractorMs. Niranjan Sharma
AA Date02-11-2022
Start Date07-01-2023
Expected Completion06-10-2023

One Time Improvement of Left Out Portion of NH-80 from km. 119.885 (Dogachhi) to km. 132.895 (Zero Mile, Bhagalpur) on EPC mode in the state of Bihar is a Bihar Road Construction Department (RCD) project under Road Division Bhagalpur., classified as a MDR. The agreement amount for this project is ₹9.83 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work completed

Frequently Asked Questions

What is the current status of the Bihar RCD project "One Time Improvement of Left Out Portion of NH-80 from km. 119.885 (Dogachhi) to"?
Status: Completed. This MDR project under Road Division Bhagalpur. (East Bihar Road Circle Bhagalpur) covers 13.01 km of road work. Expected completion: 06-10-2023.
Who is the contractor for RCD project 562?
The contractor for this project is Ms. Niranjan Sharma. Project number: 562. Division: Road Division Bhagalpur.. Administrative approval date: 02-11-2022.
What is the agreement value for this Bihar road project?
The agreement value for "One Time Improvement of Left Out Portion of NH-80 from km. 1" is ₹9.83 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Bhagalpur..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 562 "One Time Improvement of Left Out Portion of NH-80 from km. 1" is one of thousands of road improvement and construction works tracked by BiharInfraTales.