| Project No. | 39 |
| Wing | Simanchal Wing |
| Division | Road Division Bhagalpur. |
| Circle | East Bihar Road Circle Bhagalpur |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹16.46 Cr |
| Sanctioned Length | 15.86 km |
| Contractor | BABA PROJECTS PRIVATE LIMITED |
| AA Date | 29-08-2020 |
| Start Date | 23-02-2021 |
| Expected Completion | 31-12-2022 |
Work is in progress. As per revised TS No. of culverts has been increased from 4 to 8 and total length of the road is 16.006 KM
Superintending Engineer quality visit record
East Bihar Road Circle Bhagalpur · Road Division Bhagalpur.
Visited: 19 Sept 2023"View attached PDF."