MDRRCD BiharCompleted

W/S work of Bhawanipur Sadhopur Bandh road in km-0.0 to 5.5 for the year 2018-19

#706
Road Division Bhagalpur.
East Bihar Road Circle Bhagalpur
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹12.56 Cr
Length5.50 km
Start04-07-2019
Completion03-06-2020
MDR · Simanchal Wing
Road Division Bhagalpur.
TOPLINE INFRA PROJECTS PRIVATE LIMITED

Project Details

6 Fields
Project No.
706
Wing
Simanchal Wing
Division
Road Division Bhagalpur.
Circle
East Bihar Road Circle Bhagalpur
Road Type
MDR
Head
PLAN

Cost & Timeline

6 Fields
Agreement Value
₹12.56 Cr
Sanctioned Length
5.50 km
Contractor
TOPLINE INFRA PROJECTS PRIVATE LIMITED
AA Date
18-02-2019
Start Date
04-07-2019
Expected Completion
03-06-2020

W/S work of Bhawanipur Sadhopur Bandh road in km-0.0 to 5.5 for the year 2018-19 is a Bihar Road Construction Department (RCD) project under Road Division Bhagalpur., classified as a MDR. The agreement amount for this project is ₹12.56 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "W/S work of Bhawanipur Sadhopur Bandh road in km-0.0 to 5.5 for the year 2018-19"?
Status: Completed. This MDR project under Road Division Bhagalpur. (East Bihar Road Circle Bhagalpur) covers 5.50 km of road work. Expected completion: 03-06-2020.
QWho is the contractor for RCD project 706?
The contractor for this project is TOPLINE INFRA PROJECTS PRIVATE LIMITED. Project number: 706. Division: Road Division Bhagalpur.. Administrative approval date: 18-02-2019.
QWhat is the agreement value for this Bihar road project?
The agreement value for "W/S work of Bhawanipur Sadhopur Bandh road in km-0.0 to 5.5 " is ₹12.56 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Bhagalpur..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 706 "W/S work of Bhawanipur Sadhopur Bandh road in km-0.0 to 5.5 " is one of thousands of road improvement and construction works tracked by BiharInfraTales.