East Central RailwayOverdue

Supplying, spreading and compaction of blanketing material from Vaishali (Km 35) to Kesaria (incl) at scattered locations in connection with construction of Hajipur-Sagauli New BG Rail Line Project.

Estimate Cost

₹34.50 Cr

Sanctioned estimate

Tendered Cost

₹32.86 Cr

-4.8% vs estimate

Physical Progress

96%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹32.86 Cr
Progress96%
Started30-05-2022
Target DOC25-12-2025
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
100
Agency
Jyoti Construction and Engineering Pvt Ltd
At and PO-Papraur PS Barauni, Begusarai-851210
Acceptance / LOA
ECR/CAO/Con/WT/agt/203 dt 23.08.22
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹34.50 Cr
Tendered Cost
₹32.86 Cr
Physical Progress
96%
Date Started
30-05-2022
Original DOC
29-11-2023
Extended DOC
25-12-2025

Supplying, spreading and compaction of blanketing material from Vaishali (Km 35) to Kesaria (incl) at scattered locations in connection with construction of Hajipur-Sagauli New BG Rail Line Project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Jyoti Construction and Engineering Pvt. Ltd.. The tendered cost of the work is ₹32.86 Cr, and it is currently Overdue with physical progress recorded at 96%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying, spreading and compaction of blanketing material from Vaishali (Km 35)"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/s Jyoti Construction and Engineering Pvt. Ltd.. Physical progress stands at 96%. Current date of completion (DOC): 25-12-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Jyoti Construction and Engineering Pvt Ltd, At and PO-Papraur PS Barauni, Begusarai-851210. Acceptance / agreement reference: ECR/CAO/Con/WT/agt/203 dt 23.08.22. Work started on 30-05-2022.
QWhat is the cost of this railway work?
The tendered cost of "Supplying, spreading and compaction of blanketing material f" is ₹32.86 Cr (against an estimate of ₹34.50 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying, spreading and compaction of blanketing material f" is one of hundreds of railway works covered.