East Central RailwayOverdue

Construction of substructure of Major Bridge No. 111 (1x45.72m OWG), 112 (1x30.5m, OWG) on well foundation and minor Bridge No. 113 (2x2.50m RCC Box) alongwith construction of permanent diversion and linking of track between Km 48/0 to 50/0 in Tamuria-Ghoghardiha section in connection with gauge conversion of Sakri-Nirmali section of Samastipur Division

Estimate Cost

₹21.19 Cr

Sanctioned estimate

Tendered Cost

₹20.57 Cr

-2.9% vs estimate

Physical Progress

95%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹20.57 Cr
Progress95%
Started29-09-2020
Target DOC28-01-2026
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG

Work Details

5 Fields
Work No.
248
Agency
Dooars Construction Company-Jalpaiguri
Madari Road, Falakata, Jalpaiguri-735211 (WB)
Acceptance / LOA
LOA No. CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-11-20-21/00856460025726/2337 dt. 16.09.2020; CA No. ECR/CA/Con/WT/Agt/140 dated 23.11.2020
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹21.19 Cr
Tendered Cost
₹20.57 Cr
Physical Progress
95%
Date Started
29-09-2020
Original DOC
15-05-2021
Extended DOC
28-01-2026

Construction of substructure of Major Bridge No. 111 (1x45.72m OWG), 112 (1x30.5m, OWG) on well foundation and minor Bridge No. 113 (2x2.50m RCC Box) alongwith construction of permanent diversion and linking of track between Km 48/0 to 50/0 in Tamuria-Ghoghardiha section in connection with gauge conversion of Sakri-Nirmali section of Samastipur Division is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Dooars Construction Company-Jalpaiguri. The tendered cost of the work is ₹20.57 Cr, and it is currently Overdue with physical progress recorded at 95%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of substructure of Major Bridge No. 111 (1x45.72m OWG), 112 (1x30.5"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/S Dooars Construction Company-Jalpaiguri. Physical progress stands at 95%. Current date of completion (DOC): 28-01-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/S Dooars Construction Company-Jalpaiguri, Madari Road, Falakata, Jalpaiguri-735211 (WB). Acceptance / agreement reference: LOA No. CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-11-20-21/00856460025726/2337 dt. 16.09.2020; CA No. ECR/CA/Con/WT/Agt/140 dated 23.11.2020. Work started on 29-09-2020.
QWhat is the cost of this railway work?
The tendered cost of "Construction of substructure of Major Bridge No. 111 (1x45.7" is ₹20.57 Cr (against an estimate of ₹21.19 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of substructure of Major Bridge No. 111 (1x45.7" is one of hundreds of railway works covered.