East Central RailwayIn Progress

Construction of platform and FOB at Manigarchi, FOB at Lohna Road and Tamuria, RCC overhead tank with tube well at Jhanjharpur, RPF Post at Jhanjharpur, Blanketing for loop lines between Manigachi-Nirmali and other miscellaneous works in connection with gauge conversion of Sakri-Nirmali section of Samastipur Division

Estimate Cost

₹16.29 Cr

Sanctioned estimate

Tendered Cost

₹13.85 Cr

-15.0% vs estimate

Physical Progress

66%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹13.85 Cr
Progress66%
Started22-06-2021
Target DOC15-08-2026
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG

Work Details

5 Fields
Work No.
250
Agency
Lord Vishnu Constructions Private Limited-Patna
102A, Lotus Apartment, New Patliputra Colony, Patna-800013
Acceptance / LOA
LOA No. CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-57-20-21/01007930036719 dt. 10.06.2021; CA No. ECR/CAO/Con/WT/Agt/172 dt 03.09.2021
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹16.29 Cr
Tendered Cost
₹13.85 Cr
Physical Progress
66%
Date Started
22-06-2021
Original DOC
09-12-2021
Extended DOC
15-08-2026

Construction of platform and FOB at Manigarchi, FOB at Lohna Road and Tamuria, RCC overhead tank with tube well at Jhanjharpur, RPF Post at Jhanjharpur, Blanketing for loop lines between Manigachi-Nirmali and other miscellaneous works in connection with gauge conversion of Sakri-Nirmali section of Samastipur Division is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Lord Vishnu Constructions Private Limited-Patna. The tendered cost of the work is ₹13.85 Cr, and it is currently In Progress with physical progress recorded at 66%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of platform and FOB at Manigarchi, FOB at Lohna Road and Tamuria, R"?
Status: In Progress. This East Central Railway work is being executed by M/S Lord Vishnu Constructions Private Limited-Patna. Physical progress stands at 66%. Current date of completion (DOC): 15-08-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/S Lord Vishnu Constructions Private Limited-Patna, 102A, Lotus Apartment, New Patliputra Colony, Patna-800013. Acceptance / agreement reference: LOA No. CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-57-20-21/01007930036719 dt. 10.06.2021; CA No. ECR/CAO/Con/WT/Agt/172 dt 03.09.2021. Work started on 22-06-2021.
QWhat is the cost of this railway work?
The tendered cost of "Construction of platform and FOB at Manigarchi, FOB at Lohna" is ₹13.85 Cr (against an estimate of ₹16.29 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of platform and FOB at Manigarchi, FOB at Lohna" is one of hundreds of railway works covered.