East Central RailwayOverdue

Linking BG track manually, Linking level crossing, Unloading and spreading of stone ballast, leading and unloading 52 kg/60kg rails and PSC sleepers, spreding of PSC sleepers, linking and packing of BG track, PG Pts. & Xings etc. from SPJ (Excl.) to DBG (excl.) in connection with doubling of Samastipur-Darbhanga section.

Work #182
As of June 2026

Estimate Cost

₹11.94 Cr

Sanctioned estimate

Tendered Cost

₹12.04 Cr

+0.8% vs estimate

Physical Progress

65%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹12.04 Cr
Progress65%
Started30-12-2017
Target DOC22-12-2023
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ

Work Details

5 Fields
Work No.
182
Agency
J.S.& Co. At & PO-Bihat
Ratan Chowk, Begusarai
Acceptance / LOA
ECR/CAO/C/N/ETN-37-17-18 Dt 23.12.17 ** ECR/CAO/Con/WT/Agt/45 dt.23.3.2018
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹11.94 Cr
Tendered Cost
₹12.04 Cr
Physical Progress
65%
Date Started
30-12-2017
Original DOC
22-12-2019
Extended DOC
22-12-2023

Linking BG track manually, Linking level crossing, Unloading and spreading of stone ballast, leading and unloading 52 kg/60kg rails and PSC sleepers, spreding of PSC sleepers, linking and packing of BG track, PG Pts. & Xings etc. from SPJ (Excl.) to DBG (excl.) in connection with doubling of Samastipur-Darbhanga section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by J.S.& Co. At & PO-Bihat. The tendered cost of the work is ₹12.04 Cr, and it is currently Overdue with physical progress recorded at 65%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Linking BG track manually, Linking level crossing, Unloading and spreading of st"?
Status: Overdue (overdue). This East Central Railway work is being executed by J.S.& Co. At & PO-Bihat. Physical progress stands at 65%. Current date of completion (DOC): 22-12-2023.
QWho is the agency for this Bihar railway project?
The agency for this work is J.S.& Co. At & PO-Bihat, Ratan Chowk, Begusarai. Acceptance / agreement reference: ECR/CAO/C/N/ETN-37-17-18 Dt 23.12.17 ** ECR/CAO/Con/WT/Agt/45 dt.23.3.2018. Work started on 30-12-2017.
QWhat is the cost of this railway work?
The tendered cost of "Linking BG track manually, Linking level crossing, Unloading" is ₹12.04 Cr (against an estimate of ₹11.94 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Linking BG track manually, Linking level crossing, Unloading" is one of hundreds of railway works covered.