East Central RailwayIn Progress

Construction of foundation, substructure of major bridges and other allied works from Ch. 0.00 to 28.00 between Araria-Raniganj in connection with construction of Araria-Supaul New line in samastipur division of E.C. Railway.

Estimate Cost

₹99.78 Cr

Sanctioned estimate

Tendered Cost

₹91.57 Cr

-8.2% vs estimate

Physical Progress

28%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹91.57 Cr
Progress28%
Started03-08-2025
Target DOC31-05-2026
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri H R Chaudhary AEN/C/SRGR

Work Details

5 Fields
Work No.
54
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-27-23-24/00964030096772
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri H R Chaudhary AEN/C/SRGR
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹99.78 Cr
Tendered Cost
₹91.57 Cr
Physical Progress
28%
Date Started
03-08-2025
Original DOC
31-05-2026
Extended DOC
N/A

Construction of foundation, substructure of major bridges and other allied works from Ch. 0.00 to 28.00 between Araria-Raniganj in connection with construction of Araria-Supaul New line in samastipur division of E.C. Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s DURGA KRISHNA STORE PRIVATE LIMITED-GUWAHATI. The tendered cost of the work is ₹91.57 Cr, and it is currently In Progress with physical progress recorded at 28%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of foundation, substructure of major bridges and other allied works"?
Status: In Progress. This East Central Railway work is being executed by M/s DURGA KRISHNA STORE PRIVATE LIMITED-GUWAHATI. Physical progress stands at 28%. Current date of completion (DOC): 31-05-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s DURGA KRISHNA STORE PRIVATE LIMITED-GUWAHATI. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-27-23-24/00964030096772. Work started on 03-08-2025.
QWhat is the cost of this railway work?
The tendered cost of "Construction of foundation, substructure of major bridges an" is ₹91.57 Cr (against an estimate of ₹99.78 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of foundation, substructure of major bridges an" is one of hundreds of railway works covered.