East Central RailwayOverdue

Flash Butt Welding of 60Kg/52kg (90/72 UTS) New/S.H rails/rail panels of all lengths using road-cum-rail mobile flash butt welding plant for various Construction/projects of East Central Railway under Chief Administrative Officer/Construction/North/East Central Railway.

Work #340
As of June 2026

Estimate Cost

₹7.69 Cr

Sanctioned estimate

Tendered Cost

₹7.61 Cr

-1.0% vs estimate

Physical Progress

80%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹7.61 Cr
Progress80%
Started12-01-2017
Target DOC31-03-2025
Indrajit Kumar, CE/C/NW; Mintu Kumar, Secy. to CAO/C/North; Manish Kumar, AEN/Con/Ballast at Pakur

Work Details

5 Fields
Work No.
340
Agency
The India Thermit Corporation Ltd
84/22, Fazalganj, Kanpur-208012
Acceptance / LOA
ECR/CAO/Con/TS/03/16/0199/FBW/TS dt. 06.01.2017
Officer in Charge
Indrajit Kumar, CE/C/NW; Mintu Kumar, Secy. to CAO/C/North; Manish Kumar, AEN/Con/Ballast at Pakur
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹7.69 Cr
Tendered Cost
₹7.61 Cr
Physical Progress
80%
Date Started
12-01-2017
Original DOC
17-11-2020
Extended DOC
31-03-2025

Flash Butt Welding of 60Kg/52kg (90/72 UTS) New/S.H rails/rail panels of all lengths using road-cum-rail mobile flash butt welding plant for various Construction/projects of East Central Railway under Chief Administrative Officer/Construction/North/East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by The India Thermit Corporation Ltd.. The tendered cost of the work is ₹7.61 Cr, and it is currently Overdue with physical progress recorded at 80%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 7.61/11.35 (1st variation value)

?

Frequently Asked Questions

QWhat is the current status of the railway work "Flash Butt Welding of 60Kg/52kg (90/72 UTS) New/S.H rails/rail panels of all len"?
Status: Overdue (overdue). This East Central Railway work is being executed by The India Thermit Corporation Ltd.. Physical progress stands at 80%. Current date of completion (DOC): 31-03-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is The India Thermit Corporation Ltd., 84/22, Fazalganj, Kanpur-208012. Acceptance / agreement reference: ECR/CAO/Con/TS/03/16/0199/FBW/TS dt. 06.01.2017. Work started on 12-01-2017.
QWhat is the cost of this railway work?
The tendered cost of "Flash Butt Welding of 60Kg/52kg (90/72 UTS) New/S.H rails/ra" is ₹7.61 Cr (against an estimate of ₹7.69 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Flash Butt Welding of 60Kg/52kg (90/72 UTS) New/S.H rails/ra" is one of hundreds of railway works covered.