6L of Kanhauli - Ramnagar (Patna Ring Road PKG-I) from Km 0.000 to Km 39.160 of SH-78/ new NH-131G
Physical Progress
99.5%
Drone-monitored
Financial Progress
98.1%
Of awarded cost
Awarded Cost
₹797 Cr
Contract value
Length
39.16 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3213
Aerial captures
Project Progress
Stage
CC Issued
Due Date
31-12-2023
Likely Date
31-08-2024
Completion
99.5%
Physical Done
Project Timeline
Awarded
08-03-2021
Construction Started
08-03-2021
In Progress
Near Completion
-
Completed
31-08-2024
Physical vs Financial Progress
Project Details
UPC
N/05005/07001/BR
National Highway
131G
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
39.16 km
Contractor
JSP Projects Pvt Ltd. - Varaha Infra Ltd. (JV)
Project Stage
CC Issued
Drone Frames
3213 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹797.00 Cr
Capital Cost
₹939.43 Cr
Start Date
08-03-2021
PCOD Date
-
Scheduled Completion
31-12-2023
Likely Completion
31-08-2024
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 18:21:59
Contractor Profile
JSP Projects Pvt Ltd. - Varaha Infra Ltd. (JV)
Project Intelligence
Construction is 99.5% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 39.16 km on 131G, improving regional connectivity.
3213 drone frames uploaded — real-time aerial monitoring is active for this project.
6L of Kanhauli - Ramnagar (Patna Ring Road PKG-I) from Km 0.000 to Km 39.160 of SH-78/ new NH-131G is a National Highways Authority of India (NHAI) project on 131G in Bihar. The project has an awarded cost of ₹797.00 Cr and is currently **1** with physical progress at 99.5%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
3,213 frames · NHAI surveillance footage · UPC N/05005/07001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "6L of Kanhauli - Ramnagar (Patna Ring Road PKG-I) from Km 0.000 to Km 39.160 of"?
- Current physical progress: 99.5%. Financial progress: 98.1%. Project stage: CC Issued. On schedule. Scheduled completion: 31-12-2023. Likely completion: 31-08-2024.
- Who is the contractor for this NHAI highway project?
- The contractor for 6L of Kanhauli - Ramnagar (Patna Ring Road PKG-I) from Km 0.000 to Km 39.160 of SH-78/ new NH-131G is JSP Projects Pvt Ltd. - Varaha Infra Ltd. (JV). The project is under RO-Patna and covers 39.16 km on 131G.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹797.00 Crore. Total capital cost: ₹939.43 Crore. The project is on 131G in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/05005/07001/BR in NHAI?
- UPC (Unique Project Code) N/05005/07001/BR refers to "6L of Kanhauli - Ramnagar (Patna Ring Road PKG-I) from Km 0.000 to Km 39.160 of SH-78/ new NH-131G" — a National Highway project on 131G in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.