Physical Progress
99.5%
Drone-monitored
Financial Progress
98.1%
Of awarded cost
Awarded Cost
₹797 Cr
Contract value
Length
39.16 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3213
Aerial captures
Stage
CC Issued
Due Date
31-12-2023
Likely Date
31-08-2024
99.5%
Physical Done
Awarded
08-03-2021
Construction Started
08-03-2021
In Progress
Near Completion
-
Completed
31-08-2024
UPC
N/05005/07001/BR
National Highway
131G
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
39.16 km
Contractor
JSP Projects Pvt Ltd. - Varaha Infra Ltd. (JV)
Project Stage
CC Issued
Drone Frames
3213 frames
Last Flight
2026-02-24
Awarded Cost
₹797.00 Cr
Capital Cost
₹939.43 Cr
Start Date
08-03-2021
PCOD Date
-
Scheduled Completion
31-12-2023
Likely Completion
31-08-2024
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 18:21:59
JSP Projects Pvt Ltd. - Varaha Infra Ltd. (JV)
Construction is 99.5% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 39.16 km on 131G, improving regional connectivity.
3213 drone frames uploaded — real-time aerial monitoring is active for this project.
3,213 frames · NHAI surveillance footage · UPC N/05005/07001/BR