Physical Progress
19.8%
Drone-monitored
Financial Progress
18.5%
Of awarded cost
Awarded Cost
₹3012 Cr
Contract value
Length
14.52 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1505
Aerial captures
Stage
Under Construction (AD issued)
Due Date
05-09-2027
Likely Date
31-03-2029
19.8%
Physical Done
Awarded
05-09-2023
Construction Started
05-09-2023
In Progress
Near Completion
-
Completed
31-03-2029
UPC
N/05005/07003/BR
National Highway
131G
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
14.52 km
Contractor
Singla constructions Limited
Project Stage
Under Construction (AD issued)
Drone Frames
1505 frames
Last Flight
2026-03-24
Awarded Cost
₹3012.27 Cr
Capital Cost
₹6291.69 Cr
Start Date
05-09-2023
PCOD Date
-
Scheduled Completion
05-09-2027
Likely Completion
31-03-2029
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 18:25:30
Singla constructions Limited
This is a mega infrastructure project worth ₹3012 Cr — among the largest NHAI projects in the region.
Physical progress stands at 19.8%. Financial utilization at 18.5%.
Project is on schedule or ahead of planned completion date.
Covers 14.52 km on 131G, improving regional connectivity.
1505 drone frames uploaded — real-time aerial monitoring is active for this project.
1,505 frames · NHAI surveillance footage · UPC N/05005/07003/BR