19EPC 3128 Drone Frames

6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02)

UPC: N/02005/13003/BR

Physical Progress

100.0%

Drone-monitored

Financial Progress

94.2%

Of awarded cost

Awarded Cost

₹553 Cr

Contract value

Length

39.698 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

3128

Aerial captures

Project Progress

Physical Progress100.0%
Financial Progress94.2%

Stage

CC Issued & O&M by Construction Agency

Due Date

27-03-2024

Likely Date

15-05-2026

Completion

100.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

28-03-2022

Construction Started

28-03-2022

In Progress

Near Completion

-

Completed

15-05-2026

Physical vs Financial Progress

Project Details

UPC

N/02005/13003/BR

National Highway

19

Regional Office

RO-Patna

State

Bihar

Mode

EPC

Length

39.698 km

Contractor

VRC Constructions (India) Pvt. Ltd.

Project Stage

CC Issued & O&M by Construction Agency

Drone Frames

3128 frames

Last Flight

2026-06-26

Cost & Timeline

Awarded Cost

₹552.55 Cr

Capital Cost

₹1822.46 Cr

Start Date

28-03-2022

PCOD Date

-

Scheduled Completion

27-03-2024

Likely Completion

15-05-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:38:08

Contractor Profile

VRC Constructions (India) Pvt. Ltd.

RO-Patna19EPC

Project Intelligence

1

Construction is 100.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 39.698 km on 19, improving regional connectivity.

4

3128 drone frames uploaded — real-time aerial monitoring is active for this project.

6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02) is a National Highways Authority of India (NHAI) project on 19 in Bihar. The project has an awarded cost of ₹552.55 Cr and is currently 1 with physical progress at 100.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

3,128 frames · NHAI surveillance footage · UPC N/02005/13003/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 "?
Current physical progress: 100.0%. Financial progress: 94.2%. Project stage: CC Issued & O&M by Construction Agency. On schedule. Scheduled completion: 27-03-2024. Likely completion: 15-05-2026.
QWho is the contractor for this NHAI highway project?
The contractor for 6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02) is VRC Constructions (India) Pvt. Ltd.. The project is under RO-Patna and covers 39.698 km on 19.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹552.55 Crore. Total capital cost: ₹1822.46 Crore. The project is on 19 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/02005/13003/BR in NHAI?
UPC (Unique Project Code) N/02005/13003/BR refers to "6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02)" — a National Highway project on 19 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.