6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02)
Physical Progress
97.9%
Drone-monitored
Financial Progress
94.2%
Of awarded cost
Awarded Cost
₹553 Cr
Contract value
Length
39.698 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2193
Aerial captures
Project Progress
Stage
CC Issued & O&M by Construction Agency
Due Date
27-03-2024
Likely Date
15-05-2026
Completion
97.9%
Physical Done
Project Timeline
Awarded
28-03-2022
Construction Started
28-03-2022
In Progress
Near Completion
-
Completed
15-05-2026
Physical vs Financial Progress
Project Details
UPC
N/02005/13003/BR
National Highway
19
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
39.698 km
Contractor
VRC Constructions (India) Pvt. Ltd.
Project Stage
CC Issued & O&M by Construction Agency
Drone Frames
2193 frames
Last Flight
2026-02-23
Cost & Timeline
Awarded Cost
₹552.55 Cr
Capital Cost
₹1822.46 Cr
Start Date
28-03-2022
PCOD Date
-
Scheduled Completion
27-03-2024
Likely Completion
15-05-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 09:18:33
Contractor Profile
VRC Constructions (India) Pvt. Ltd.
Project Intelligence
Construction is 97.9% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 39.698 km on 19, improving regional connectivity.
2193 drone frames uploaded — real-time aerial monitoring is active for this project.
6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02) is a National Highways Authority of India (NHAI) project on 19 in Bihar. The project has an awarded cost of ₹552.55 Cr and is currently 1 with physical progress at 97.9%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,193 frames · NHAI surveillance footage · UPC N/02005/13003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 "?
- Current physical progress: 97.9%. Financial progress: 94.2%. Project stage: CC Issued & O&M by Construction Agency. On schedule. Scheduled completion: 27-03-2024. Likely completion: 15-05-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for 6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02) is VRC Constructions (India) Pvt. Ltd.. The project is under RO-Patna and covers 39.698 km on 19.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹552.55 Crore. Total capital cost: ₹1822.46 Crore. The project is on 19 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/02005/13003/BR in NHAI?
- UPC (Unique Project Code) N/02005/13003/BR refers to "6L of Aurangabad to Bihar-Jharkhand border (Chordaha) section from km. 209.827 to Km. 249.525 of NH-19 (PKG-02)" — a National Highway project on 19 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.