Physical Progress
23.7%
Drone-monitored
Financial Progress
16.4%
Of awarded cost
Awarded Cost
₹520 Cr
Contract value
Length
29.827 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2303
Aerial captures
Stage
Under Construction (AD issued)
Due Date
17-12-2026
Likely Date
17-12-2026
23.7%
Physical Done
Awarded
18-12-2024
Construction Started
18-12-2024
In Progress
Near Completion
-
Completed
17-12-2026
UPC
N/02005/13002/BR
National Highway
19
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
29.827 km
Contractor
Ashoka Buildcon Limited
Project Stage
Under Construction (AD issued)
Drone Frames
2303 frames
Last Flight
2026-02-22
Awarded Cost
₹520.00 Cr
Capital Cost
₹1054.46 Cr
Start Date
18-12-2024
PCOD Date
-
Scheduled Completion
17-12-2026
Likely Completion
17-12-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 09:12:11
Ashoka Buildcon Limited
Physical progress stands at 23.7%. Financial utilization at 16.4%.
Project is on schedule or ahead of planned completion date.
Covers 29.827 km on 19, improving regional connectivity.
2303 drone frames uploaded — real-time aerial monitoring is active for this project.
2,303 frames · NHAI surveillance footage · UPC N/02005/13002/BR