Physical Progress
99.8%
Drone-monitored
Financial Progress
98.4%
Of awarded cost
Awarded Cost
₹565 Cr
Contract value
Length
192.4 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
20036
Aerial captures
Stage
Under Construction (AD issued)
Due Date
10-03-2014
Likely Date
30-06-2026
99.8%
Physical Done
Awarded
12-09-2011
Construction Started
12-09-2011
In Progress
Near Completion
-
Completed
30-06-2026
UPC
N/02005/12001/BR
National Highway
19
Regional Office
RO-Patna
State
Bihar
Mode
BOT Toll
Length
192.4 km
Contractor
Soma - Isolux
Project Stage
Under Construction (AD issued)
Drone Frames
20036 frames
Last Flight
2026-01-27
Awarded Cost
₹565.00 Cr
Capital Cost
₹3241.56 Cr
Start Date
12-09-2011
PCOD Date
-
Scheduled Completion
10-03-2014
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 15:16:32
Soma - Isolux
Construction is 99.8% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 192.4 km on 19, improving regional connectivity.
20036 drone frames uploaded — real-time aerial monitoring is active for this project.
20,036 frames · NHAI surveillance footage · UPC N/02005/12001/BR