Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2

UPC: N/02005/12001/BR

Physical Progress

99.9%

Drone-monitored

Financial Progress

98.4%

Of awarded cost

Awarded Cost

₹565 Cr

Contract value

Length

192.4 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

18382

Aerial captures

Project Progress

Physical Progress99.9%
Financial Progress98.4%

Stage

Under Construction (AD issued)

Due Date

10-03-2014

Likely Date

30-09-2026

Completion

99.9%

Physical Done

DoneRemaining

Project Timeline

Awarded

12-09-2011

Construction Started

12-09-2011

In Progress

Near Completion

-

Completed

30-09-2026

Physical vs Financial Progress

Project Details

UPC

N/02005/12001/BR

National Highway

19

Regional Office

RO-Patna

State

Bihar

Mode

BOT Toll

Length

192.4 km

Contractor

Soma - Isolux

Project Stage

Under Construction (AD issued)

Drone Frames

18382 frames

Last Flight

2026-07-27

Cost & Timeline

Awarded Cost

₹565.00 Cr

Capital Cost

₹3241.56 Cr

Start Date

12-09-2011

PCOD Date

-

Scheduled Completion

10-03-2014

Likely Completion

30-09-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:37:13

Contractor Profile

Soma - Isolux

RO-Patna19BOT Toll

Project Intelligence

1

Construction is 99.9% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 192.4 km on 19, improving regional connectivity.

4

18382 drone frames uploaded — real-time aerial monitoring is active for this project.

Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2 is a National Highways Authority of India (NHAI) project on 19 in Bihar. The project has an awarded cost of ₹565.00 Cr and is currently ongoing with physical progress at 99.9%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

18,382 frames · NHAI surveillance footage · UPC N/02005/12001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2"?
Current physical progress: 99.9%. Financial progress: 98.4%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 10-03-2014. Likely completion: 30-09-2026.
QWho is the contractor for this NHAI highway project?
The contractor for Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2 is Soma - Isolux. The project is under RO-Patna and covers 192.4 km on 19.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹565.00 Crore. Total capital cost: ₹3241.56 Crore. The project is on 19 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/02005/12001/BR in NHAI?
UPC (Unique Project Code) N/02005/12001/BR refers to "Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2" — a National Highway project on 19 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.