Transmission & DistributionIPM · Central Project#616671

Transmission System under ISTS for evacuation of Power from Kudankulam Unit-3&4 [2x1000 MW] [SPV Name POWERGRID Kudankulam Tarnsmission Limited]

Ministry of PowerTamil Nadu
Revised Cost: ₹548 CrUtilization: 40.0%

Original Cost

₹548 Cr

Baseline estimate

On budget

Revised Cost

₹548 Cr

Latest approved cost

Expenditure

₹219 Cr

Spent to date

Utilization

40.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹329 Cr

Budget left

Budget Utilization

40.0%
0%25%50%75%100%

Spent

₹219 Cr

Remaining

₹329 Cr

Total

₹548 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2026

Revised Completion

31/03/2027

Completed

Project Details

Project Code616671
SectorTransmission & Distribution
MinistryMinistry of Power
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹548 Cr
Revised Cost₹548 Cr
Expenditure₹219 Cr
Original End Date31/12/2026
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹548 Cr — no cost escalation recorded.

Expenditure stands at ₹219 Cr, which is 40.0% of the revised project cost.

Remaining budget: ₹329 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission System under ISTS for evacuation of Power from Kudankulam Unit-3&4 [2x1000 MW] [SPV Name POWERGRID Kudankulam Tarnsmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹548.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission System under ISTS for evacuation of Power from Kudankulam Unit-3&4 "?
Transmission System under ISTS for evacuation of Power from Kudankulam Unit-3&4 [2x1000 MW] [SPV Name POWERGRID Kudankulam Tarnsmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Tamil Nadu. Original cost: ₹548 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹548 Cr has not been significantly revised. Expenditure: ₹219 Cr (40.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission System under ISTS for evacuation of Power from is under the Ministry of Power in the Transmission & Distribution sector. Project code: 616671. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System under ISTS for evacuation of Power from is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.