Original Cost
₹548 Cr
Baseline estimate
Revised Cost
₹548 Cr
Latest approved cost
Expenditure
₹121 Cr
Spent to date
Utilization
22.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹427 Cr
Budget left
Spent
₹121 Cr
Remaining
₹427 Cr
Total
₹548 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹548 Cr — no cost escalation recorded.
Expenditure stands at ₹121 Cr, which is 22.0% of the revised project cost.
Remaining budget: ₹427 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.