Original Cost
₹1382 Cr
Baseline estimate
Revised Cost
₹1382 Cr
Latest approved cost
Expenditure
₹567 Cr
Spent to date
Utilization
41.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹815 Cr
Budget left
Spent
₹567 Cr
Remaining
₹815 Cr
Total
₹1382 Cr
Project Approved
Construction / Implementation
Original End Date
29/08/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1382 Cr — no cost escalation recorded.
Expenditure stands at ₹567 Cr, which is 41.0% of the revised project cost.
Remaining budget: ₹815 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.