Original Cost
₹1111 Cr
Baseline estimate
Revised Cost
₹1111 Cr
Latest approved cost
Expenditure
₹6 Cr
Spent to date
Utilization
0.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1106 Cr
Budget left
Spent
₹6 Cr
Remaining
₹1106 Cr
Total
₹1111 Cr
Project Approved
Construction / Implementation
Original End Date
11/02/2028
Revised Completion
Completed
Project is within original budget of ₹1111 Cr — no cost escalation recorded.
Expenditure stands at ₹6 Cr, which is 0.5% of the revised project cost.
Remaining budget: ₹1106 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.