Transmission & DistributionIPM · Central Project#619228

Transmission System Strengthening for integration of additional RE Potential at Davanagere [0.25 GW] and Bellary [2.75 GW]

Ministry of PowerKarnataka
Revised Cost: ₹1111 CrUtilization: 4.0%

Original Cost

₹1111 Cr

Baseline estimate

On budget

Revised Cost

₹1111 Cr

Latest approved cost

Expenditure

₹44 Cr

Spent to date

Utilization

4.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1067 Cr

Budget left

Budget Utilization

4.0%
0%25%50%75%100%

Spent

₹44 Cr

Remaining

₹1067 Cr

Total

₹1111 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

11/02/2028

Revised Completion

Completed

Project Details

Project Code619228
SectorTransmission & Distribution
MinistryMinistry of Power
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹1111 Cr
Revised Cost₹1111 Cr
Expenditure₹44 Cr
Original End Date11/02/2028
Revised DateN/A

Project Intelligence

Project is within original budget of ₹1111 Cr — no cost escalation recorded.

Expenditure stands at ₹44 Cr, which is 4.0% of the revised project cost.

Remaining budget: ₹1067 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission System Strengthening for integration of additional RE Potential at Davanagere [0.25 GW] and Bellary [2.75 GW] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹1111.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission System Strengthening for integration of additional RE Potential at "?
Transmission System Strengthening for integration of additional RE Potential at Davanagere [0.25 GW] and Bellary [2.75 GW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Karnataka. Original cost: ₹1111 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1111 Cr has not been significantly revised. Expenditure: ₹44 Cr (4.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission System Strengthening for integration of additio is under the Ministry of Power in the Transmission & Distribution sector. Project code: 619228. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System Strengthening for integration of additio is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.