Transmission & DistributionIPM · Central Project#617183

Transmission system strengthening at Kurnool- III PS for integration of additional RE generation projects [POWERGRID Kurnool III PS RE Transmission Limited]

Ministry of PowerAndhra Pradesh
Revised Cost: ₹2886 CrUtilization: 34.1%

Original Cost

₹2886 Cr

Baseline estimate

On budget

Revised Cost

₹2886 Cr

Latest approved cost

Expenditure

₹983 Cr

Spent to date

Utilization

34.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1903 Cr

Budget left

Budget Utilization

34.1%
0%25%50%75%100%

Spent

₹983 Cr

Remaining

₹1903 Cr

Total

₹2886 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2027

Revised Completion

Completed

Project Details

Project Code617183
SectorTransmission & Distribution
MinistryMinistry of Power
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2886 Cr
Revised Cost₹2886 Cr
Expenditure₹983 Cr
Original End Date31/12/2027
Revised DateN/A

Project Intelligence

Project is within original budget of ₹2886 Cr — no cost escalation recorded.

Expenditure stands at ₹983 Cr, which is 34.1% of the revised project cost.

Remaining budget: ₹1903 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission system strengthening at Kurnool- III PS for integration of additional RE generation projects [POWERGRID Kurnool III PS RE Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹2886.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission system strengthening at Kurnool- III PS for integration of addition"?
Transmission system strengthening at Kurnool- III PS for integration of additional RE generation projects [POWERGRID Kurnool III PS RE Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Andhra Pradesh. Original cost: ₹2886 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹2886 Cr has not been significantly revised. Expenditure: ₹983 Cr (34.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission system strengthening at Kurnool- III PS for int is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617183. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission system strengthening at Kurnool- III PS for int is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.