Original Cost
₹2886 Cr
Baseline estimate
Revised Cost
₹2886 Cr
Latest approved cost
Expenditure
₹722 Cr
Spent to date
Utilization
25.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2165 Cr
Budget left
Spent
₹722 Cr
Remaining
₹2165 Cr
Total
₹2886 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2027
Revised Completion
Completed
Project is within original budget of ₹2886 Cr — no cost escalation recorded.
Expenditure stands at ₹722 Cr, which is 25.0% of the revised project cost.
Remaining budget: ₹2165 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.