Transmission System Strengthening at Davanagere for Integration of RE Generation [SPV Name - POWERGRID Davanagere Power Transmission Limited]
Original Cost
₹379 Cr
Baseline estimate
Revised Cost
₹379 Cr
Latest approved cost
Expenditure
₹17 Cr
Spent to date
Utilization
4.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹362 Cr
Budget left
Budget Utilization
4.5%Spent
₹17 Cr
Remaining
₹362 Cr
Total
₹379 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/09/2027
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹379 Cr — no cost escalation recorded.
Expenditure stands at ₹17 Cr, which is 4.5% of the revised project cost.
Remaining budget: ₹362 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Transmission System Strengthening at Davanagere for Integration of RE Generation [SPV Name - POWERGRID Davanagere Power Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹379.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Transmission System Strengthening at Davanagere for Integration of RE Generation"?
- Transmission System Strengthening at Davanagere for Integration of RE Generation [SPV Name - POWERGRID Davanagere Power Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Karnataka. Original cost: ₹379 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹379 Cr has not been significantly revised. Expenditure: ₹17 Cr (4.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Transmission System Strengthening at Davanagere for Integrat is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617803. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System Strengthening at Davanagere for Integrat is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.