Transmission system for evacuation of power from REZ in Rajasthan 20 GW under Phase-III part H
Original Cost
₹1910 Cr
Baseline estimate
Revised Cost
₹1910 Cr
Latest approved cost
Expenditure
₹1853 Cr
Spent to date
Utilization
97.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹57 Cr
Budget left
Budget Utilization
97.0%Spent
₹1853 Cr
Remaining
₹57 Cr
Total
₹1910 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/04/2025
Revised Completion
30/06/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1910 Cr — no cost escalation recorded.
Expenditure stands at ₹1853 Cr, which is 97.0% of the revised project cost.
Remaining budget: ₹57 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Transmission system for evacuation of power from REZ in Rajasthan 20 GW under Phase-III part H is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹1910.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Transmission system for evacuation of power from REZ in Rajasthan 20 GW under Ph"?
- Transmission system for evacuation of power from REZ in Rajasthan 20 GW under Phase-III part H is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Rajasthan. Original cost: ₹1910 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1910 Cr has not been significantly revised. Expenditure: ₹1853 Cr (97.0% of cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Transmission system for evacuation of power from REZ in Raja is under the Ministry of Power in the Transmission & Distribution sector. Project code: 611948. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission system for evacuation of power from REZ in Raja is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.