Original Cost
₹5357 Cr
Baseline estimate
Revised Cost
₹5357 Cr
Latest approved cost
Expenditure
₹1446 Cr
Spent to date
Utilization
27.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹3911 Cr
Budget left
Spent
₹1446 Cr
Remaining
₹3911 Cr
Total
₹5357 Cr
Project Approved
Construction / Implementation
Original End Date
11/11/2026
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹5357 Cr — no cost escalation recorded.
Expenditure stands at ₹1446 Cr, which is 27.0% of the revised project cost.
Remaining budget: ₹3911 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.