Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5 GW][Jaisalmer/Barmer Complex] Part B [SPV Name POWERGRID Sirohi Transmission Limited]
Original Cost
₹3279 Cr
Baseline estimate
Revised Cost
₹3279 Cr
Latest approved cost
Expenditure
₹1978 Cr
Spent to date
Utilization
60.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1301 Cr
Budget left
Budget Utilization
60.3%Spent
₹1978 Cr
Remaining
₹1301 Cr
Total
₹3279 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/08/2026
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹3279 Cr — no cost escalation recorded.
Expenditure stands at ₹1978 Cr, which is 60.3% of the revised project cost.
Remaining budget: ₹1301 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5 GW][Jaisalmer/Barmer Complex] Part B [SPV Name POWERGRID Sirohi Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹3279.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5"?
- Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5 GW][Jaisalmer/Barmer Complex] Part B [SPV Name POWERGRID Sirohi Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Rajasthan. Original cost: ₹3279 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹3279 Cr has not been significantly revised. Expenditure: ₹1978 Cr (60.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Transmission System for Evacuation of Power from Rajasthan R is under the Ministry of Power in the Transmission & Distribution sector. Project code: 615332. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System for Evacuation of Power from Rajasthan R is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.