Transmission & DistributionIPM · Central Project#615344

Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5GW] [Jaisalmer/Barmer Complex] Part H1 [POWERGRID KURAWAR TRANSMISSION LIMITED]

Ministry of PowerMadhya Pradesh
Revised Cost: ₹3674 CrUtilization: 47.0%

Original Cost

₹3674 Cr

Baseline estimate

On budget

Revised Cost

₹3674 Cr

Latest approved cost

Expenditure

₹1727 Cr

Spent to date

Utilization

47.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1947 Cr

Budget left

Budget Utilization

47.0%
0%25%50%75%100%

Spent

₹1727 Cr

Remaining

₹1947 Cr

Total

₹3674 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/10/2026

Revised Completion

30/06/2027

Completed

Project Details

Project Code615344
SectorTransmission & Distribution
MinistryMinistry of Power
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹3674 Cr
Revised Cost₹3674 Cr
Expenditure₹1727 Cr
Original End Date14/10/2026
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹3674 Cr — no cost escalation recorded.

Expenditure stands at ₹1727 Cr, which is 47.0% of the revised project cost.

Remaining budget: ₹1947 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5GW] [Jaisalmer/Barmer Complex] Part H1 [POWERGRID KURAWAR TRANSMISSION LIMITED] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹3674.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5."?
Transmission System for Evacuation of Power from Rajasthan REZ Ph-IV [Part-2 5.5GW] [Jaisalmer/Barmer Complex] Part H1 [POWERGRID KURAWAR TRANSMISSION LIMITED] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Madhya Pradesh. Original cost: ₹3674 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹3674 Cr has not been significantly revised. Expenditure: ₹1727 Cr (47.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission System for Evacuation of Power from Rajasthan R is under the Ministry of Power in the Transmission & Distribution sector. Project code: 615344. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System for Evacuation of Power from Rajasthan R is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.