TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN REZ PH -IV [PART-2 5.5 GW] [JAISALMER/BARMER COMPLEX] PART F [SPV Name POWERGRID BARMER I TRANSMISSION LIMITED]
Original Cost
₹2735 Cr
Baseline estimate
Revised Cost
₹2735 Cr
Latest approved cost
Expenditure
₹1203 Cr
Spent to date
Utilization
44.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1532 Cr
Budget left
Budget Utilization
44.0%Spent
₹1203 Cr
Remaining
₹1532 Cr
Total
₹2735 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/11/2026
Revised Completion
30/06/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹2735 Cr — no cost escalation recorded.
Expenditure stands at ₹1203 Cr, which is 44.0% of the revised project cost.
Remaining budget: ₹1532 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN REZ PH -IV [PART-2 5.5 GW] [JAISALMER/BARMER COMPLEX] PART F [SPV Name POWERGRID BARMER I TRANSMISSION LIMITED] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹2735.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN REZ PH -IV [PART-2 5."?
- TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN REZ PH -IV [PART-2 5.5 GW] [JAISALMER/BARMER COMPLEX] PART F [SPV Name POWERGRID BARMER I TRANSMISSION LIMITED] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Rajasthan. Original cost: ₹2735 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹2735 Cr has not been significantly revised. Expenditure: ₹1203 Cr (44.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN R is under the Ministry of Power in the Transmission & Distribution sector. Project code: 615338. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN R is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.