Original Cost
₹2735 Cr
Baseline estimate
Revised Cost
₹2735 Cr
Latest approved cost
Expenditure
₹930 Cr
Spent to date
Utilization
34.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1805 Cr
Budget left
Spent
₹930 Cr
Remaining
₹1805 Cr
Total
₹2735 Cr
Project Approved
Construction / Implementation
Original End Date
06/11/2026
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹2735 Cr — no cost escalation recorded.
Expenditure stands at ₹930 Cr, which is 34.0% of the revised project cost.
Remaining budget: ₹1805 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.