Transmission & DistributionIPM · Central Project#612855

Transmission System for Evacuation of Power from Potential Energy Renewable Zone in Khavda Area of Gujarat under Ph-IV [7GW] Part E2

Ministry of PowerGujarat
Revised Cost: ₹697 CrUtilization: 91.0%

Original Cost

₹697 Cr

Baseline estimate

On budget

Revised Cost

₹697 Cr

Latest approved cost

Expenditure

₹634 Cr

Spent to date

Utilization

91.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹63 Cr

Budget left

Budget Utilization

91.0%
0%25%50%75%100%

Spent

₹634 Cr

Remaining

₹63 Cr

Total

₹697 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/05/2026

Revised Completion

30/09/2026

Completed

Project Details

Project Code612855
SectorTransmission & Distribution
MinistryMinistry of Power
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹697 Cr
Revised Cost₹697 Cr
Expenditure₹634 Cr
Original End Date30/05/2026
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹697 Cr — no cost escalation recorded.

Expenditure stands at ₹634 Cr, which is 91.0% of the revised project cost.

Remaining budget: ₹63 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission System for Evacuation of Power from Potential Energy Renewable Zone in Khavda Area of Gujarat under Ph-IV [7GW] Part E2 is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹697.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission System for Evacuation of Power from Potential Energy Renewable Zone"?
Transmission System for Evacuation of Power from Potential Energy Renewable Zone in Khavda Area of Gujarat under Ph-IV [7GW] Part E2 is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Gujarat. Original cost: ₹697 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹697 Cr has not been significantly revised. Expenditure: ₹634 Cr (91.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission System for Evacuation of Power from Potential E is under the Ministry of Power in the Transmission & Distribution sector. Project code: 612855. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System for Evacuation of Power from Potential E is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.