Transmission & DistributionIPM · Central Project#612139

Transmission system for Evacuation of Additional 7 GW RE power from Khavda RE park under Phase-III Part B [Vataman Transmission Limited]

Ministry of PowerGujarat
Revised Cost: ₹4231 CrUtilization: 75.1%

Original Cost

₹4231 Cr

Baseline estimate

On budget

Revised Cost

₹4231 Cr

Latest approved cost

Expenditure

₹3176 Cr

Spent to date

Utilization

75.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1055 Cr

Budget left

Budget Utilization

75.1%
0%25%50%75%100%

Spent

₹3176 Cr

Remaining

₹1055 Cr

Total

₹4231 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/12/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code612139
SectorTransmission & Distribution
MinistryMinistry of Power
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹4231 Cr
Revised Cost₹4231 Cr
Expenditure₹3176 Cr
Original End Date25/12/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹4231 Cr — no cost escalation recorded.

Expenditure stands at ₹3176 Cr, which is 75.1% of the revised project cost.

Remaining budget: ₹1055 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission system for Evacuation of Additional 7 GW RE power from Khavda RE park under Phase-III Part B [Vataman Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹4231.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission system for Evacuation of Additional 7 GW RE power from Khavda RE pa"?
Transmission system for Evacuation of Additional 7 GW RE power from Khavda RE park under Phase-III Part B [Vataman Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Gujarat. Original cost: ₹4231 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹4231 Cr has not been significantly revised. Expenditure: ₹3176 Cr (75.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission system for Evacuation of Additional 7 GW RE pow is under the Ministry of Power in the Transmission & Distribution sector. Project code: 612139. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission system for Evacuation of Additional 7 GW RE pow is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.