Original Cost
₹4231 Cr
Baseline estimate
Revised Cost
₹4231 Cr
Latest approved cost
Expenditure
₹2539 Cr
Spent to date
Utilization
60.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1692 Cr
Budget left
Spent
₹2539 Cr
Remaining
₹1692 Cr
Total
₹4231 Cr
Project Approved
Construction / Implementation
Original End Date
25/12/2025
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹4231 Cr — no cost escalation recorded.
Expenditure stands at ₹2539 Cr, which is 60.0% of the revised project cost.
Remaining budget: ₹1692 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.