Transmission & DistributionIPM · Central Project#611967

Transmission Scheme for Solar Energy Zone in Ananthpuram 2500MW and Kurnool 1000MW

Ministry of PowerAndhra Pradesh
Revised Cost: ₹823 CrUtilization: 97.0%

Original Cost

₹823 Cr

Baseline estimate

On budget

Revised Cost

₹823 Cr

Latest approved cost

Expenditure

₹798 Cr

Spent to date

Utilization

97.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹25 Cr

Budget left

Budget Utilization

97.0%
0%25%50%75%100%

Spent

₹798 Cr

Remaining

₹25 Cr

Total

₹823 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2025

Revised Completion

31/05/2026

Completed

Project Details

Project Code611967
SectorTransmission & Distribution
MinistryMinistry of Power
StateAndhra Pradesh
Data Month2026-05

Financial Summary

Original Cost₹823 Cr
Revised Cost₹823 Cr
Expenditure₹798 Cr
Original End Date30/09/2025
Revised Date31/05/2026

Project Intelligence

Project is within original budget of ₹823 Cr — no cost escalation recorded.

Expenditure stands at ₹798 Cr, which is 97.0% of the revised project cost.

Remaining budget: ₹25 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission Scheme for Solar Energy Zone in Ananthpuram 2500MW and Kurnool 1000MW is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹823.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission Scheme for Solar Energy Zone in Ananthpuram 2500MW and Kurnool 1000"?
Transmission Scheme for Solar Energy Zone in Ananthpuram 2500MW and Kurnool 1000MW is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Andhra Pradesh. Original cost: ₹823 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹823 Cr has not been significantly revised. Expenditure: ₹798 Cr (97.0% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Transmission Scheme for Solar Energy Zone in Ananthpuram 250 is under the Ministry of Power in the Transmission & Distribution sector. Project code: 611967. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission Scheme for Solar Energy Zone in Ananthpuram 250 is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.