Transmission Network Expansion in Gujarat to increase its ATC from ISTS Part B
Original Cost
₹4546 Cr
Baseline estimate
Revised Cost
₹4546 Cr
Latest approved cost
Expenditure
₹4528 Cr
Spent to date
Utilization
99.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹18 Cr
Budget left
Budget Utilization
99.6%Spent
₹4528 Cr
Remaining
₹18 Cr
Total
₹4546 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
12/06/2023
Revised Completion
31/05/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹4546 Cr — no cost escalation recorded.
Expenditure stands at ₹4528 Cr, which is 99.6% of the revised project cost.
Remaining budget: ₹18 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Transmission Network Expansion in Gujarat to increase its ATC from ISTS Part B is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹4546.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Transmission Network Expansion in Gujarat to increase its ATC from ISTS Part B"?
- Transmission Network Expansion in Gujarat to increase its ATC from ISTS Part B is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Maharashtra. Original cost: ₹4546 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹4546 Cr has not been significantly revised. Expenditure: ₹4528 Cr (99.6% of cost). Data as of 2026-04.
- QWhich ministry is responsible for this project?
- Transmission Network Expansion in Gujarat to increase its AT is under the Ministry of Power in the Transmission & Distribution sector. Project code: 400005. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission Network Expansion in Gujarat to increase its AT is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.