Tehri Pumped Storage Plant Project [4x250 MW]
Original Cost
₹4826 Cr
Baseline estimate
Revised Cost
₹8339 Cr
Latest approved cost
Expenditure
₹8213 Cr
Spent to date
Utilization
98.5%
Of revised budget
Cost Status
+72.8%
+₹3513 Cr increase
Remaining
₹126 Cr
Budget left
Budget Utilization
98.5%Spent
₹8213 Cr
Remaining
₹126 Cr
Total
₹8339 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹4826 Cr
Revised Cost
₹8339 Cr
Increase
+₹3513 Cr
Escalation
+72.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/06/2022
Revised Completion
31/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹3513 Cr (72.8%) from the original estimate of ₹4826 Cr.
Expenditure stands at ₹8213 Cr, which is 98.5% of the revised project cost.
Remaining budget: ₹126 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Tehri Pumped Storage Plant Project [4x250 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹4826.00 Cr, later revised to ₹8339.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Tehri Pumped Storage Plant Project [4x250 MW]"?
- Tehri Pumped Storage Plant Project [4x250 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Uttarakhand. Original cost: ₹4826 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹4826 Cr and has been revised to ₹8339 Cr — a cost overrun of +72.8%. Expenditure to date: ₹8213 Cr (98.5% of revised cost). Data as of 2026-02.
- QWhich ministry is responsible for this project?
- Tehri Pumped Storage Plant Project [4x250 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602193. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tehri Pumped Storage Plant Project [4x250 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.