Electricity GenerationIPM · Central Project#611699

186 MW Tato-I H E Project

Ministry of PowerArunachal Pradesh
Revised Cost: ₹1750 CrUtilization: 4.6%

Original Cost

₹1750 Cr

Baseline estimate

On budget

Revised Cost

₹1750 Cr

Latest approved cost

Expenditure

₹80 Cr

Spent to date

Utilization

4.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1670 Cr

Budget left

Budget Utilization

4.6%
0%25%50%75%100%

Spent

₹80 Cr

Remaining

₹1670 Cr

Total

₹1750 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

29/07/2029

Revised Completion

Completed

Project Details

Project Code611699
SectorElectricity Generation
MinistryMinistry of Power
StateArunachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1750 Cr
Revised Cost₹1750 Cr
Expenditure₹80 Cr
Original End Date29/07/2029
Revised DateN/A

Project Intelligence

Project is within original budget of ₹1750 Cr — no cost escalation recorded.

Expenditure stands at ₹80 Cr, which is 4.6% of the revised project cost.

Remaining budget: ₹1670 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

186 MW Tato-I H E Project is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹1750.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "186 MW Tato-I H E Project"?
186 MW Tato-I H E Project is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Arunachal Pradesh. Original cost: ₹1750 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1750 Cr has not been significantly revised. Expenditure: ₹80 Cr (4.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
186 MW Tato-I H E Project is under the Ministry of Power in the Electricity Generation sector. Project code: 611699. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 186 MW Tato-I H E Project is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.