240MW Heo HE Project
Original Cost
₹1939 Cr
Baseline estimate
Revised Cost
₹1939 Cr
Latest approved cost
Expenditure
₹107 Cr
Spent to date
Utilization
5.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1832 Cr
Budget left
Budget Utilization
5.5%Spent
₹107 Cr
Remaining
₹1832 Cr
Total
₹1939 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/07/2029
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1939 Cr — no cost escalation recorded.
Expenditure stands at ₹107 Cr, which is 5.5% of the revised project cost.
Remaining budget: ₹1832 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
240MW Heo HE Project is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹1939.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "240MW Heo HE Project"?
- 240MW Heo HE Project is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Arunachal Pradesh. Original cost: ₹1939 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1939 Cr has not been significantly revised. Expenditure: ₹107 Cr (5.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 240MW Heo HE Project is under the Ministry of Power in the Electricity Generation sector. Project code: 611698. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 240MW Heo HE Project is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.