Original Cost
₹9791 Cr
Baseline estimate
Revised Cost
₹9791 Cr
Latest approved cost
Expenditure
₹1687 Cr
Spent to date
Utilization
17.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹8104 Cr
Budget left
Spent
₹1687 Cr
Remaining
₹8104 Cr
Total
₹9791 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2029
Revised Completion
30/11/2029
Completed
Project is within original budget of ₹9791 Cr — no cost escalation recorded.
Expenditure stands at ₹1687 Cr, which is 17.2% of the revised project cost.
Remaining budget: ₹8104 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.