Original Cost
₹2416 Cr
Baseline estimate
Revised Cost
₹2416 Cr
Latest approved cost
Expenditure
₹2 Cr
Spent to date
Utilization
0.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2414 Cr
Budget left
Spent
₹2 Cr
Remaining
₹2414 Cr
Total
₹2416 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2032
Revised Completion
Completed
Project is within original budget of ₹2416 Cr — no cost escalation recorded.
Expenditure stands at ₹2 Cr, which is 0.1% of the revised project cost.
Remaining budget: ₹2414 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.