Original Cost
₹385 Cr
Baseline estimate
Revised Cost
₹385 Cr
Latest approved cost
Expenditure
₹363 Cr
Spent to date
Utilization
94.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹22 Cr
Budget left
Spent
₹363 Cr
Remaining
₹22 Cr
Total
₹385 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2020
Revised Completion
31/05/2026
Completed
Project is within original budget of ₹385 Cr — no cost escalation recorded.
Expenditure stands at ₹363 Cr, which is 94.3% of the revised project cost.
Remaining budget: ₹22 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.