CoalIPM · Central Project#400142

Pachwara South Coal Block

Ministry of CoalJharkhand
Revised Cost: ₹2243 CrUtilization: 64.6%

Original Cost

₹2243 Cr

Baseline estimate

On budget

Revised Cost

₹2243 Cr

Latest approved cost

Expenditure

₹1448 Cr

Spent to date

Utilization

64.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹795 Cr

Budget left

Budget Utilization

64.6%
0%25%50%75%100%

Spent

₹1448 Cr

Remaining

₹795 Cr

Total

₹2243 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2028

Revised Completion

Completed

Project Details

Project Code400142
SectorCoal
MinistryMinistry of Coal
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹2243 Cr
Revised Cost₹2243 Cr
Expenditure₹1448 Cr
Original End Date30/09/2028
Revised DateN/A

Project Intelligence

Project is within original budget of ₹2243 Cr — no cost escalation recorded.

Expenditure stands at ₹1448 Cr, which is 64.6% of the revised project cost.

Remaining budget: ₹795 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Coal. Ministry: Ministry of Coal.

Pachwara South Coal Block is a centrally-funded infrastructure project under Ministry of Coal, in the Coal sector. The original approved cost is ₹2243.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project " Pachwara South Coal Block"?
Pachwara South Coal Block is a centrally-funded infrastructure project under the Ministry of Coal, tracked through the Investment Project Monitoring (IPM) system. Sector: Coal. State: Jharkhand. Original cost: ₹2243 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹2243 Cr has not been significantly revised. Expenditure: ₹1448 Cr (64.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Pachwara South Coal Block is under the Ministry of Coal in the Coal sector. Project code: 400142. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pachwara South Coal Block is one of several Bihar projects tracked under the Coal sector on the IPM system.