SteelIPM · Central Project#617249

Replacement of existing Grinders in CRM-I & II at Bokaro Steel Plant

Ministry of SteelJharkhand
Revised Cost: ₹212 CrUtilization: 67.5%

Original Cost

₹212 Cr

Baseline estimate

On budget

Revised Cost

₹212 Cr

Latest approved cost

Expenditure

₹143 Cr

Spent to date

Utilization

67.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹69 Cr

Budget left

Budget Utilization

67.5%
0%25%50%75%100%

Spent

₹143 Cr

Remaining

₹69 Cr

Total

₹212 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/01/2027

Revised Completion

Completed

Project Details

Project Code617249
SectorSteel
MinistryMinistry of Steel
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹212 Cr
Revised Cost₹212 Cr
Expenditure₹143 Cr
Original End Date27/01/2027
Revised DateN/A

Project Intelligence

Project is within original budget of ₹212 Cr — no cost escalation recorded.

Expenditure stands at ₹143 Cr, which is 67.5% of the revised project cost.

Remaining budget: ₹69 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Steel. Ministry: Ministry of Steel.

Replacement of existing Grinders in CRM-I & II at Bokaro Steel Plant is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹212.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Replacement of existing Grinders in CRM-I & II at Bokaro Steel Plant"?
Replacement of existing Grinders in CRM-I & II at Bokaro Steel Plant is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Jharkhand. Original cost: ₹212 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹212 Cr has not been significantly revised. Expenditure: ₹143 Cr (67.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Replacement of existing Grinders in CRM-I & II at Bokaro Ste is under the Ministry of Steel in the Steel sector. Project code: 617249. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Replacement of existing Grinders in CRM-I & II at Bokaro Ste is one of several Bihar projects tracked under the Steel sector on the IPM system.