SteelIPM · Central Project#589703

Implementation of Treatment System-2 Under ZLD at RSP

Ministry of SteelOdisha
Revised Cost: ₹216 CrUtilization: 68.5%

Original Cost

₹216 Cr

Baseline estimate

On budget

Revised Cost

₹216 Cr

Latest approved cost

Expenditure

₹148 Cr

Spent to date

Utilization

68.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹68 Cr

Budget left

Budget Utilization

68.5%
0%25%50%75%100%

Spent

₹148 Cr

Remaining

₹68 Cr

Total

₹216 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2026

Revised Completion

Completed

Project Details

Project Code589703
SectorSteel
MinistryMinistry of Steel
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹216 Cr
Revised Cost₹216 Cr
Expenditure₹148 Cr
Original End Date30/09/2026
Revised DateN/A

Project Intelligence

Project is within original budget of ₹216 Cr — no cost escalation recorded.

Expenditure stands at ₹148 Cr, which is 68.5% of the revised project cost.

Remaining budget: ₹68 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Steel. Ministry: Ministry of Steel.

Implementation of Treatment System-2 Under ZLD at RSP is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹216.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Implementation of Treatment System-2 Under ZLD at RSP"?
Implementation of Treatment System-2 Under ZLD at RSP is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Odisha. Original cost: ₹216 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹216 Cr has not been significantly revised. Expenditure: ₹148 Cr (68.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Implementation of Treatment System-2 Under ZLD at RSP is under the Ministry of Steel in the Steel sector. Project code: 589703. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Implementation of Treatment System-2 Under ZLD at RSP is one of several Bihar projects tracked under the Steel sector on the IPM system.