Installation of 140 TPH Walking Beam type Reheating Furnace in Plate Mill at BSP
Original Cost
₹268 Cr
Baseline estimate
Revised Cost
₹268 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹268 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹268 Cr
Total
₹268 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹268 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹268 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.
Installation of 140 TPH Walking Beam type Reheating Furnace in Plate Mill at BSP is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹268.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Installation of 140 TPH Walking Beam type Reheating Furnace in Plate Mill at BSP"?
- Installation of 140 TPH Walking Beam type Reheating Furnace in Plate Mill at BSP is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Chhattisgarh. Original cost: ₹268 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹268 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Installation of 140 TPH Walking Beam type Reheating Furnace is under the Ministry of Steel in the Steel sector. Project code: 505491. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Installation of 140 TPH Walking Beam type Reheating Furnace is one of several Bihar projects tracked under the Steel sector on the IPM system.