Original Cost
₹1105 Cr
Baseline estimate
Revised Cost
₹1105 Cr
Latest approved cost
Expenditure
₹790 Cr
Spent to date
Utilization
71.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹315 Cr
Budget left
Spent
₹790 Cr
Remaining
₹315 Cr
Total
₹1105 Cr
Project Approved
Construction / Implementation
Original End Date
15/05/2025
Revised Completion
30/09/2025
Completed
Project is within original budget of ₹1105 Cr — no cost escalation recorded.
Expenditure stands at ₹790 Cr, which is 71.5% of the revised project cost.
Remaining budget: ₹315 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Steel. Ministry: Ministry of Steel.