SteelIPM · Central Project#400065

Installation of 4th Slab Caster along with its Auxiliaries and a New Ladle Furnace in SMS-II at Rourkela Steel Plant

Ministry of SteelOdisha
Revised Cost: ₹1105 CrUtilization: 71.5%

Original Cost

₹1105 Cr

Baseline estimate

On budget

Revised Cost

₹1105 Cr

Latest approved cost

Expenditure

₹790 Cr

Spent to date

Utilization

71.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹315 Cr

Budget left

Budget Utilization

71.5%
0%25%50%75%100%

Spent

₹790 Cr

Remaining

₹315 Cr

Total

₹1105 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/05/2025

Revised Completion

30/09/2025

Completed

Project Details

Project Code400065
SectorSteel
MinistryMinistry of Steel
StateOdisha
Data Month2025-11

Financial Summary

Original Cost₹1105 Cr
Revised Cost₹1105 Cr
Expenditure₹790 Cr
Original End Date15/05/2025
Revised Date30/09/2025

Project Intelligence

Project is within original budget of ₹1105 Cr — no cost escalation recorded.

Expenditure stands at ₹790 Cr, which is 71.5% of the revised project cost.

Remaining budget: ₹315 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Steel. Ministry: Ministry of Steel.

Installation of 4th Slab Caster along with its Auxiliaries and a New Ladle Furnace in SMS-II at Rourkela Steel Plant is a centrally-funded infrastructure project under Ministry of Steel, in the Steel sector. The original approved cost is ₹1105.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Installation of 4th Slab Caster along with its Auxiliaries and a New Ladle Furna"?
Installation of 4th Slab Caster along with its Auxiliaries and a New Ladle Furnace in SMS-II at Rourkela Steel Plant is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Steel. State: Odisha. Original cost: ₹1105 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1105 Cr has not been significantly revised. Expenditure: ₹790 Cr (71.5% of cost). Data as of 2025-11.
QWhich ministry is responsible for this project?
Installation of 4th Slab Caster along with its Auxiliaries a is under the Ministry of Steel in the Steel sector. Project code: 400065. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Installation of 4th Slab Caster along with its Auxiliaries a is one of several Bihar projects tracked under the Steel sector on the IPM system.