Original Cost
₹511 Cr
Baseline estimate
Revised Cost
₹511 Cr
Latest approved cost
Expenditure
₹489 Cr
Spent to date
Utilization
95.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹22 Cr
Budget left
Spent
₹489 Cr
Remaining
₹22 Cr
Total
₹511 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2016
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹511 Cr — no cost escalation recorded.
Expenditure stands at ₹489 Cr, which is 95.6% of the revised project cost.
Remaining budget: ₹22 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.