Raghunathpur Thermal Power Station Phase II [2X660 MW] at Raghunathpur, Purulia, West Bengal
Original Cost
₹17.7K Cr
Baseline estimate
Revised Cost
₹17.7K Cr
Latest approved cost
Expenditure
₹2396 Cr
Spent to date
Utilization
13.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹15.3K Cr
Budget left
Budget Utilization
13.6%Spent
₹2396 Cr
Remaining
₹15.3K Cr
Total
₹17.7K Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
28/08/2029
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Mega infrastructure project worth ₹17.7K Cr — among the largest central projects in West Bengal.
Project is within original budget of ₹17.7K Cr — no cost escalation recorded.
Expenditure stands at ₹2396 Cr, which is 13.6% of the revised project cost.
Remaining budget: ₹15.3K Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.
Raghunathpur Thermal Power Station Phase II [2X660 MW] at Raghunathpur, Purulia, West Bengal is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹17673.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Raghunathpur Thermal Power Station Phase II [2X660 MW] at Raghunathpur, Purulia,"?
- Raghunathpur Thermal Power Station Phase II [2X660 MW] at Raghunathpur, Purulia, West Bengal is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: West Bengal. Original cost: ₹17673 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹17673 Cr has not been significantly revised. Expenditure: ₹2396 Cr (13.6% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Raghunathpur Thermal Power Station Phase II [2X660 MW] at Ra is under the Ministry of Power in the Electricity Generation sector. Project code: 400062. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Raghunathpur Thermal Power Station Phase II [2X660 MW] at Ra is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.