Urban Public TransportIPM · Central Project +5.5% overrun#617225

PCMC To Nigdi- Extension Of North South Corridor Of Phase-1

Ministry of Housing & Urban AffairsMaharashtra
Revised Cost: ₹960 CrUtilization: 35.0%Overrun: +₹50 Cr

Original Cost

₹910 Cr

Baseline estimate

+6% overrun

Revised Cost

₹960 Cr

Latest approved cost

Expenditure

₹336 Cr

Spent to date

Utilization

35.0%

Of revised budget

Escalated

Cost Status

+5.5%

+₹50 Cr increase

Remaining

₹624 Cr

Budget left

Budget Utilization

35.0%
0%25%50%75%100%

Spent

₹336 Cr

Remaining

₹624 Cr

Total

₹960 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹910 Cr

Revised Cost

₹960 Cr

Increase

+₹50 Cr

Escalation

+5.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/01/2027

Revised Completion

Completed

Project Details

Project Code617225
SectorUrban Public Transport
MinistryMinistry of Housing & Urban Affairs
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹910 Cr
Revised Cost₹960 Cr
Expenditure₹336 Cr
Original End Date31/01/2027
Revised DateN/A

Project Intelligence

Cost has increased by ₹50 Cr (5.5%) from the original estimate of ₹910 Cr.

Expenditure stands at ₹336 Cr, which is 35.0% of the revised project cost.

Remaining budget: ₹624 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.

PCMC To Nigdi- Extension Of North South Corridor Of Phase-1 is a centrally-funded infrastructure project under Ministry of Housing & Urban Affairs, in the Urban Public Transport sector. The original approved cost is ₹910.00 Cr, later revised to ₹960.18 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "PCMC To Nigdi- Extension Of North South Corridor Of Phase-1"?
PCMC To Nigdi- Extension Of North South Corridor Of Phase-1 is a centrally-funded infrastructure project under the Ministry of Housing & Urban Affairs, tracked through the Investment Project Monitoring (IPM) system. Sector: Urban Public Transport. State: Maharashtra. Original cost: ₹910 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹910 Cr and has been revised to ₹960 Cr — a cost overrun of +5.5%. Expenditure to date: ₹336 Cr (35.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
PCMC To Nigdi- Extension Of North South Corridor Of Phase-1 is under the Ministry of Housing & Urban Affairs in the Urban Public Transport sector. Project code: 617225. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. PCMC To Nigdi- Extension Of North South Corridor Of Phase-1 is one of several Bihar projects tracked under the Urban Public Transport sector on the IPM system.