Original Cost
₹8380 Cr
Baseline estimate
Revised Cost
₹8380 Cr
Latest approved cost
Expenditure
₹6070 Cr
Spent to date
Utilization
72.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2310 Cr
Budget left
Spent
₹6070 Cr
Remaining
₹2310 Cr
Total
₹8380 Cr
Project Approved
Construction / Implementation
Original End Date
26/05/2024
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹8380 Cr — no cost escalation recorded.
Expenditure stands at ₹6070 Cr, which is 72.4% of the revised project cost.
Remaining budget: ₹2310 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.