Original Cost
₹10.8K Cr
Baseline estimate
Revised Cost
₹12.9K Cr
Latest approved cost
Expenditure
₹12.5K Cr
Spent to date
Utilization
96.9%
Of revised budget
Cost Status
+20.0%
+₹2152 Cr increase
Remaining
₹404 Cr
Budget left
Spent
₹12.5K Cr
Remaining
₹404 Cr
Total
₹12.9K Cr
Original Cost
₹10.8K Cr
Revised Cost
₹12.9K Cr
Increase
+₹2152 Cr
Escalation
+20.0%
Project Approved
Construction / Implementation
Original End Date
31/03/2018
Revised Completion
31/05/2026
Completed
Mega infrastructure project worth ₹12.9K Cr — among the largest central projects in Gujarat.
Cost has increased by ₹2152 Cr (20.0%) from the original estimate of ₹10.8K Cr.
Expenditure stands at ₹12.5K Cr, which is 96.9% of the revised project cost.
Remaining budget: ₹404 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.