Electricity GenerationIPM · Central Project +8.8% overrun#400261

Patratu Thermal Power Station Expansion Project Phase-I [3x800 MW]

Ministry of PowerJharkhand
Revised Cost: ₹20.3K CrUtilization: 95.6%Overrun: +₹1634 Cr

Original Cost

₹18.7K Cr

Baseline estimate

+9% overrun

Revised Cost

₹20.3K Cr

Latest approved cost

Expenditure

₹19.4K Cr

Spent to date

Utilization

95.6%

Of revised budget

Escalated

Cost Status

+8.8%

+₹1634 Cr increase

Remaining

₹897 Cr

Budget left

Budget Utilization

95.6%
0%25%50%75%100%

Spent

₹19.4K Cr

Remaining

₹897 Cr

Total

₹20.3K Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹18.7K Cr

Revised Cost

₹20.3K Cr

Increase

+₹1634 Cr

Escalation

+8.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2023

Revised Completion

30/04/2027

Completed

Project Details

Project Code400261
SectorElectricity Generation
MinistryMinistry of Power
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹18.7K Cr
Revised Cost₹20.3K Cr
Expenditure₹19.4K Cr
Original End Date31/03/2023
Revised Date30/04/2027

Project Intelligence

Mega infrastructure project worth ₹20.3K Cr — among the largest central projects in Jharkhand.

Cost has increased by ₹1634 Cr (8.8%) from the original estimate of ₹18.7K Cr.

Expenditure stands at ₹19.4K Cr, which is 95.6% of the revised project cost.

Remaining budget: ₹897 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Patratu Thermal Power Station Expansion Project Phase-I [3x800 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹18668.00 Cr, later revised to ₹20302.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Patratu Thermal Power Station Expansion Project Phase-I [3x800 MW]"?
Patratu Thermal Power Station Expansion Project Phase-I [3x800 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Jharkhand. Original cost: ₹18668 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹18668 Cr and has been revised to ₹20302 Cr — a cost overrun of +8.8%. Expenditure to date: ₹19406 Cr (95.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Patratu Thermal Power Station Expansion Project Phase-I [3x8 is under the Ministry of Power in the Electricity Generation sector. Project code: 400261. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Patratu Thermal Power Station Expansion Project Phase-I [3x8 is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.