Original Cost
₹18.7K Cr
Baseline estimate
Revised Cost
₹20.3K Cr
Latest approved cost
Expenditure
₹19.1K Cr
Spent to date
Utilization
93.9%
Of revised budget
Cost Status
+8.8%
+₹1634 Cr increase
Remaining
₹1237 Cr
Budget left
Spent
₹19.1K Cr
Remaining
₹1237 Cr
Total
₹20.3K Cr
Original Cost
₹18.7K Cr
Revised Cost
₹20.3K Cr
Increase
+₹1634 Cr
Escalation
+8.8%
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
30/04/2027
Completed
Mega infrastructure project worth ₹20.3K Cr — among the largest central projects in Jharkhand.
Cost has increased by ₹1634 Cr (8.8%) from the original estimate of ₹18.7K Cr.
Expenditure stands at ₹19.1K Cr, which is 93.9% of the revised project cost.
Remaining budget: ₹1237 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.