Original Cost
₹389 Cr
Baseline estimate
Revised Cost
₹389 Cr
Latest approved cost
Expenditure
₹132 Cr
Spent to date
Utilization
34.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹257 Cr
Budget left
Spent
₹132 Cr
Remaining
₹257 Cr
Total
₹389 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project is within original budget of ₹389 Cr — no cost escalation recorded.
Expenditure stands at ₹132 Cr, which is 34.1% of the revised project cost.
Remaining budget: ₹257 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Coal. Ministry: Ministry of Coal.