Electricity GenerationIPM · Central Project +56.9% overrun#602525

Pakal Dul [Drangdhuran] Hydroelectric Project, 1000 MW

Ministry of PowerJammu & Kashmir
Revised Cost: ₹12.7K CrUtilization: 77.8%Overrun: +₹4616 Cr

Original Cost

₹8112 Cr

Baseline estimate

+57% overrun

Revised Cost

₹12.7K Cr

Latest approved cost

Expenditure

₹9906 Cr

Spent to date

Utilization

77.8%

Of revised budget

Escalated

Cost Status

+56.9%

+₹4616 Cr increase

Remaining

₹2823 Cr

Budget left

Budget Utilization

77.8%
0%25%50%75%100%

Spent

₹9906 Cr

Remaining

₹2823 Cr

Total

₹12.7K Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹8112 Cr

Revised Cost

₹12.7K Cr

Increase

+₹4616 Cr

Escalation

+56.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/04/2020

Revised Completion

31/12/2026

Completed

Project Details

Project Code602525
SectorElectricity Generation
MinistryMinistry of Power
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹8112 Cr
Revised Cost₹12.7K Cr
Expenditure₹9906 Cr
Original End Date27/04/2020
Revised Date31/12/2026

Project Intelligence

Mega infrastructure project worth ₹12.7K Cr — among the largest central projects in Jammu & Kashmir.

Cost has increased by ₹4616 Cr (56.9%) from the original estimate of ₹8112 Cr.

Expenditure stands at ₹9906 Cr, which is 77.8% of the revised project cost.

Remaining budget: ₹2823 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Pakal Dul [Drangdhuran] Hydroelectric Project, 1000 MW is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹8112.00 Cr, later revised to ₹12728.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pakal Dul [Drangdhuran] Hydroelectric Project, 1000 MW"?
Pakal Dul [Drangdhuran] Hydroelectric Project, 1000 MW is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Jammu & Kashmir. Original cost: ₹8112 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹8112 Cr and has been revised to ₹12728 Cr — a cost overrun of +56.9%. Expenditure to date: ₹9906 Cr (77.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Pakal Dul [Drangdhuran] Hydroelectric Project, 1000 MW is under the Ministry of Power in the Electricity Generation sector. Project code: 602525. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pakal Dul [Drangdhuran] Hydroelectric Project, 1000 MW is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.