Original Cost
₹8112 Cr
Baseline estimate
Revised Cost
₹12.7K Cr
Latest approved cost
Expenditure
₹9314 Cr
Spent to date
Utilization
73.2%
Of revised budget
Cost Status
+56.9%
+₹4616 Cr increase
Remaining
₹3414 Cr
Budget left
Spent
₹9314 Cr
Remaining
₹3414 Cr
Total
₹12.7K Cr
Original Cost
₹8112 Cr
Revised Cost
₹12.7K Cr
Increase
+₹4616 Cr
Escalation
+56.9%
Project Approved
Construction / Implementation
Original End Date
27/04/2020
Revised Completion
31/12/2026
Completed
Mega infrastructure project worth ₹12.7K Cr — among the largest central projects in Jammu & Kashmir.
Cost has increased by ₹4616 Cr (56.9%) from the original estimate of ₹8112 Cr.
Expenditure stands at ₹9314 Cr, which is 73.2% of the revised project cost.
Remaining budget: ₹3414 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.