Original Cost
₹5111 Cr
Baseline estimate
Revised Cost
₹6700 Cr
Latest approved cost
Expenditure
₹5578 Cr
Spent to date
Utilization
83.3%
Of revised budget
Cost Status
+31.1%
+₹1589 Cr increase
Remaining
₹1122 Cr
Budget left
Spent
₹5578 Cr
Remaining
₹1122 Cr
Total
₹6700 Cr
Original Cost
₹5111 Cr
Revised Cost
₹6700 Cr
Increase
+₹1589 Cr
Escalation
+31.1%
Project Approved
Construction / Implementation
Original End Date
31/12/2018
Revised Completion
31/03/2027
Completed
Cost has increased by ₹1589 Cr (31.1%) from the original estimate of ₹5111 Cr.
Expenditure stands at ₹5578 Cr, which is 83.3% of the revised project cost.
Remaining budget: ₹1122 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.