Original Cost
₹1207 Cr
Baseline estimate
Revised Cost
₹1207 Cr
Latest approved cost
Expenditure
₹311 Cr
Spent to date
Utilization
25.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹896 Cr
Budget left
Spent
₹311 Cr
Remaining
₹896 Cr
Total
₹1207 Cr
Project Approved
Construction / Implementation
Original End Date
31/07/2025
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹1207 Cr — no cost escalation recorded.
Expenditure stands at ₹311 Cr, which is 25.8% of the revised project cost.
Remaining budget: ₹896 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.